Blacktopping of Diggar road delay was caused due to non-availability of the blacktopping lying machine.

Leh:  Sept 9, 2013 – VisitLadakh.com – The Councilor Diskit Tsewang Rigzin today called on the Executive Engineer PMGSY and expressed serious concern over the delay being caused with lying of blacktopping of Diggar road which is being constructed under PMGSY. The Councilor urged the PMGSY department to expedite the process of execution of blacktopping works at Diggar and have it completed in the month of September itself in view of the winter season approaching soon.

Executive Engineer PMGSY told the Councilor that the delay was caused due to non-availability of the blacktopping lying machine. He however assured that blacktopping works will be started within three to four days as the machine is being brought to Digger from Kargil district.